Metro Line 12 status, answered

कल्याण-तळोजा मेट्रो १२

The questions people ask about Mumbai Metro Line 12, Kalyan to Taloja. Each answer shows how sure it is and where it comes from. Checked .

When will Mumbai Metro Line 12 open?

No official opening date has been published. The latest reported target is May 2028 (reported in December 2025). An earlier reported target was 31 Dec 2027, and the 2019 project report had assumed 31 Oct 2024. MMRDA's project page gives no date.

Sources conflictFree Press Journal (opens source in a new tab)

How much of Line 12 is built?

MMRDA's progress table for 31 Aug 2026 puts pile works at 37.12%, pile cap works at 31.54%, pier works at 25.88%, pier cap works (erection) at 26.84%, U-girder works (erection) at 18.75%. Loksatta reported on 27 Sep 2026, quoting unnamed MMRDA sources, that 53.87% of the whole line is complete; MMRDA itself publishes no overall figure.

VerifiedMMRDA (opens source in a new tab)Reportedloksatta.com (opens source in a new tab)

What is the route of Metro Line 12?

Kalyan to Amandoot (Taloja), via Dombivli MIDC, Kalyan Growth Centre, Wadavli, Turbhe and Pisarve. The line is 23.57 km long, fully elevated, with 19 stations. It runs above Kalyan-Shilphata Road from Kalyan to Sonarpada.

VerifiedMMRDA (opens source in a new tab)

See the route on the map

Which stations are on Line 12?

19 stations, in order: Kalyan, APMC Kalyan, Ganesh Nagar, Pisavali Gaon, Golavli, Dombivli MIDC, Sagaon, Sonarpada, Manpada, Hedutane, Kolegaon, Nilje Gaon, Vadavli (Khu.), Bale, Waklan, Turbhe, Pisarve Depot, Pisarve, Amandoot.

VerifiedMMRDA (opens source in a new tab)

A page for every station

Where does Line 12 connect with other lines?

At Kalyan, with Metro Line 5 (Thane-Bhiwandi-Kalyan). At Hedutane, with Metro Line 14 (Vikhroli-Badlapur). At Amandoot, with Navi Mumbai Metro Line 1. Line 12 continues Metro Line 5 (Thane-Bhiwandi-Kalyan) south from Kalyan.

VerifiedMMRDA (opens source in a new tab)

How much does Metro Line 12 cost?

MMRDA gives a project completion cost of Rs 5,865 crore, including land, taxes and interest during construction. Funding has not been confirmed by a primary source.

VerifiedMMRDA (opens source in a new tab)UnverifiedMMRDA DPR (2019) (opens source in a new tab)

Who is building Line 12?

MMRDA (Mumbai Metropolitan Region Development Authority) is building the line. Gawar Constructions Ltd holds the civil contract for the viaduct and all 19 stations (package CA-240, awarded in March 2024).

VerifiedMMRDA (opens source in a new tab)ReportedThe Metro Rail Guy (opens source in a new tab)

Where is the Line 12 depot?

At Nilje, on about 31 hectares.

VerifiedMMRDA (opens source in a new tab)

Which trains will run on Line 12?

No train maker has been chosen yet. The trains are part of the systems tender MMRDA floated in June 2026. The 2019 project report plans 3-car air-conditioned trains, growing to 6 cars, with a top operating speed of 80 km/h.

ReportedMetro Rail News (opens source in a new tab)VerifiedMMRDA DPR (2019) (opens source in a new tab)

How many people will use Line 12?

About 2.62 lakh riders a day by 2031, as projected. MMRDA says it will cut current travel time by 50% to 75%, depending on road conditions.

VerifiedMMRDA (opens source in a new tab)VerifiedMMRDA (opens source in a new tab)

Is Line 12A the same as Line 12?

No. Metro Line 12A (Kalyan Phata to Taloja via Dahisar Mori) is a separate project: 18.4 km elevated corridor with 12 stations, joining Line 12 near Khutari village. Administrative approval of Rs 8,414.53 crore reported in February 2026. Its figures are not counted in Line 12's.

ReportedNewsband (opens source in a new tab)

What else is Metro Line 12 called?

Mumbai Metro Line 12 is also called Metro 12 or Kalyan-Dombivli-Taloja Metro. It is part of the Orange Line, as the southern extension of Metro Line 5.

VerifiedMMRDA (opens source in a new tab)