Nilje Gaon metro station
निळजे गाव मेट्रो स्थानक
Station 12 of 19 on Mumbai Metro Line 12, which will run fully elevated from Kalyan to Taloja. Elevated. Under construction.
No ground photo yet
Dated photos of Nilje Gaon from the street will appear here.
- Where
19.15755, 73.09456 (approximate, from the 2019 project report)
- Along the line
11.1 km along the 2019 alignment (DPR chainage 11,093.376 m)
- Next stations
- Towards Kalyan: Kolegaon
- Towards Taloja: Vadavli (Khu.)
- Interchange
None announced
- Around the station
- On a straight alignment near Nilje village; a river crossing follows at about ch. 12,100 m to 12,180 mVerifiedMMRDA DPR (2019) (opens source in a new tab)
- Line 12 depot is at Nilje (31 ha)VerifiedMMRDA (opens source in a new tab)
- Construction
Under construction (civil works across the corridor)
MMRDA publishes corridor-wide progress only, not per-station progress.
- When it opens
No date has been announced for this station on its own. For Line 12 as a whole, the reported target is May 2028; an earlier reported target was 31 Dec 2027.
Sources conflictFree Press Journal (opens source in a new tab)
- Name
Nilje Gaon
Also spelled Nilaje Gaon.
ReportedThe Metro Rail Guy (opens source in a new tab)
In Marathi: निळजे गाव