Hedutane metro station
हेदुटणे मेट्रो स्थानक
Station 10 of 19 on Mumbai Metro Line 12, which will run fully elevated from Kalyan to Taloja. Elevated. Under construction.
No ground photo yet
Dated photos of Hedutane from the street will appear here.
- Where
19.17144, 73.09907 (approximate, from the 2019 project report)
- Along the line
8.9 km along the 2019 alignment (DPR chainage 8,947.974 m)
- Interchange
Metro Line 14 (Vikhroli-Badlapur)
- Around the station
- In Hedutane villageVerifiedMMRDA DPR (2019) (opens source in a new tab)
- Construction
Under construction (civil works across the corridor)
MMRDA publishes corridor-wide progress only, not per-station progress.
- When it opens
No date has been announced for this station on its own. For Line 12 as a whole, the reported target is May 2028; an earlier reported target was 31 Dec 2027.
Sources conflictFree Press Journal (opens source in a new tab)
- Name
Hedutane
Interchange listed by MMRDA.
ReportedThe Metro Rail Guy (opens source in a new tab)
In Marathi: हेदुटणे